Research on Back Analysis of Parameters for Excavation of the Underground Cavern Group of A Large-scale Hydro-power Station by Using Orthogonal Optimization
Yang, Wendong; Gao, Xichao; Zhang, Yanmei; Yang, Jia; Wang, Gang; Zhang, Qiangyong
刊名PROGRESS IN CIVIL ENGINEERING, PTS 1-4
2012
卷号170-173页码:3356-3360
关键词Back Analysis Orthogonal Design Effect Calculation Underground Cavern
DOI10.4028/www.scientific.net/AMM.170-173.3356
会议名称2nd International Conference on Civil Engineering, Architecture and Building Materials (CEABM 2012)
URL标识查看原文
会议日期MAY 25-27, 2012
内容类型期刊论文
URI标识http://www.corc.org.cn/handle/1471x/5210526
专题山东大学
作者单位1.China Univ Petr, Coll Pipeline & Civil Engn, Qingdao 266580, Shandong, Peoples R China.
2.[Yang, Jia
3.Wan
推荐引用方式
GB/T 7714
Yang, Wendong,Gao, Xichao,Zhang, Yanmei,et al. Research on Back Analysis of Parameters for Excavation of the Underground Cavern Group of A Large-scale Hydro-power Station by Using Orthogonal Optimization[J]. PROGRESS IN CIVIL ENGINEERING, PTS 1-4,2012,170-173:3356-3360.
APA Yang, Wendong,Gao, Xichao,Zhang, Yanmei,Yang, Jia,Wang, Gang,&Zhang, Qiangyong.(2012).Research on Back Analysis of Parameters for Excavation of the Underground Cavern Group of A Large-scale Hydro-power Station by Using Orthogonal Optimization.PROGRESS IN CIVIL ENGINEERING, PTS 1-4,170-173,3356-3360.
MLA Yang, Wendong,et al."Research on Back Analysis of Parameters for Excavation of the Underground Cavern Group of A Large-scale Hydro-power Station by Using Orthogonal Optimization".PROGRESS IN CIVIL ENGINEERING, PTS 1-4 170-173(2012):3356-3360.
个性服务
查看访问统计
相关权益政策
暂无数据
收藏/分享
所有评论 (0)
暂无评论
 

除非特别说明,本系统中所有内容都受版权保护,并保留所有权利。


©版权所有 ©2017 CSpace - Powered by CSpace